Construction Updates - September 2006

View of the first floor classroom portion of the building.
What’s Happening:
- The concrete floors in the gymnasium and cafeteria are being placed this week.
- Construction of exterior masonry walls for the classroom wings and interior walls is on-going. (see photo at top left). They are working from the east end towards the west.
- In-wall electrical and mechanical installation on-going.
The light gauge steel trusses for the gymnasium will be set next week.
- The curved steel arch for the stage was set last week (see photo on left ).
Construction Phases
Phase I May 2005—February 2006
Design and planning - Completed
Phase II April 2006—August 2007
Construction of new building
Phase III June 2007— October 2007
Demolition of old building
Site restoration
Masonry and steel work on gym and cafeteria walls continues.

Steel arch framing the stage has been set.

|