Construction Update for October

What’s Happening:
First floor exterior masonry walls are 95% complete.
Trusses have been set in the gym and cafeteria.. (see photos)
In-wall electrical and mechanical construction work continues.
All first floor concrete floors have been placed.
Setting of the metal deck and second floor precast concrete flooring will begin the week of October 30th.
Underground utilities will begin in mid-November. Construction Phases
Phase I May 2005—February 2006
Design and planning - Completed
Phase II April 2006—August 2007
Construction of new building
Phase III June 2007— October 2007
Demolition of old building
Site restoration
|