Construction Update for November 2006
Whats Happening:

- Metal trusses in area C of the building have been set.
- Pre-cast concrete flooring panels for the second floor have been set. (see photo at left)
- The roof enclosure (metal deck and plywood) over the gym and cafeteria is complete.
- Construction of the masonry walls for the second floor has begun.
- Installation of duct work in the classrooms has begun.
- Installation of underground storm piping has begun.
- Installation of main stairwells has begun.
- Doors and windows have been enclosed to provide temporary heat for contractors to continue work.
Construction Phases
Phase I May 2005—February 2006
Design and planning - Completed
Phase II April 2006—August 2007
Construction of new building
Phase III June 2007— October 2007
Demolition of old building
|