May 2007 Construction Updates
What’s Happening:

Installation of the stonework removed and saved from the original Milan entrance has been completed.
- Ceramic tile in the first floor toilet rooms has been completed.
- Exterior brick installation and cleaning is 99% completed.
- Exterior window installation will be completed this month.
- Stone work pieces recovered from the original entrance have been installed (see photo).
- Ceiling grid in first floor classrooms, hallways, gymnasium and cafeteria is complete (see photo).
- Installation of classroom lights on the first floor has begun.
- Interior masonry and drywall on the second floor is complete.
- Installation of piping and duct work on the second floor continues.

Typical classroom, looking from the door toward the windows. Classrooms on the first floor have been painted, ceiling grid installed.
Construction Phases
Phase I May 2005—February 2006
Design and planning - Completed
Phase II April 2006—August 2007
Construction of new building
Phase III June 2007— October 2007
Demolition of old building
|