New Sorth River Construction Update March 2007
What's Happening
-
Installation of the roof trusses will be completed mid-March.
-
Installation of the metal decking on the west side of the building will begin the week of Mar. 19.
-
The boiler room is 90% complete.
-
Exterior brick on the east side of the building is being laid.
-
The brick on the interior stage wall area is nearing completion.
-
Installation of the duct work and piping in classrooms continues.
-
Drywall installation in the first floor classrooms is complete.
-
Basketball backboards have been installed in the gymnasium.
-
Abatement and demolition contracts will be awarded this month.
Construction Phases
Phase I May 2005—February 2006
Design and planning - Completed
Phase II April 2006—August 2007
Construction of new building
Phase III June 2007— October 2007
Demolition of old building

Above: The front entrance to the new building, with offices to the left and the Media Center on the right.
Below: Interior pictures of a typical first floor classroom with drywall and duct work.

|