What's Happening:
Exterior brickwork is nearing completion. (See photo)
Installation of the exterior windows is near completion.
Installation of the metal roof begins April 25.
Interior painting on the first floor has begun.
Installation of the duct work and pipe on the second floor has begun.
Gymnasium basketball backstops have been installed.
Installation of the hydraulic lift and cab for the elevator has begun.
Brickwork on the face of the stage in the cafeteria has been set.
Installation of the walk-in freezer and refrigerator will begin by the end of the month.
If you have any questions, please call Sandy Denewith at (586) 783-6550 x 1121 and leave a message. Your call will be returned as soon as possible.
Photos
These photos display the progress of construction. April 10, 2007
 Exterior View
Stage
Construction Phases
Phase I May 2005—February 2006 Design and planning - Completed
Phase II April 2006—August 2007 Construction of new building
Phase III June 2007— October 2007 Demolition of old building and site
restoration
|