Construction Updates November 2006
Project Update
-
The new storm drain that runs from LCHS, behind MSC to Graham Elementary has been installed and rough grading has been completed. Seeding will be done in the spring.
-
Steel frame work and joists for B wing in the gym area are installed. (see photo)
-
Masonry walls and piers are under construction. (see photo)
-
Mechanical and electrical work continues. Concrete footings are complete in both A and B wings.
-
Existing crock pipe has been replaced in the gym area.
-
Asphalt work is being done on the east side, at the bus loop exit and the east entrance to the student parking lot.
-
Completion of the project is scheduled for August 2007.


Summer/Fall Construction Projects
-
Improvements to underground drainage on site
-
Installation of artificial turf on football field
-
Resurfacing of track
-
Demolition of existing gymnasium
-
Construction of new three-court gymnasium and sports lobby
-
Construction of new main entrance
-
Construction of new student commons area and school store
|